Objectives
Task 9.1. Coordination and Communication
• Management and coordination of the Work Package, including monitoring of work progress, budget spending and
reporting to the project management.
• Organisation of WP meetings as well as meetings with other WPs and coordinating presentation of results within
AIDAinnova and to the detector community.
Task 9.2. Pixel charge readout
• Optimised pixel tile pattern for the DUNE LAr far detector
• Design and prototype for large scale tile-based anode plane
Task 9.3. Vertical Drift charge readout
• Novel Vertical Drift perforated anodes charge readout design evolving from the Dual-phase charge readout stack
• Development and tests of novel design of the Charge Readout Plane (CRP) integration surface of the Vertical Drift
perforated anodes
• Developments and tests of integrated cold electronics, new feedthrough chimneys design
• Developments in associated digitisation hardware and online data treatment
Task 9.4. Light readout
• Characterisation of new photon detection methods, calibration devices and readout electronics
• Implementation and characterisation of a more efficient light collection system in NP02/ProtoDUNE phase II (Xe
doping and Wave Length Shifting (WLS) combined with reflective foils)
• Dissemination of R&D results and NP02/ProtoDUNE II light-collection performance (web site)
Tasks
Task # | Task Name | Task Leader |
---|---|---|
9.1 | Coordination and Communication | |
9.2 | Pixel charge readout | |
9.3 | Vertical Drift charge readout | |
9.4 | Light readout |
Milestones
MS # | Milestone Name | Lead beneficiary | Due Date (in months) | Means of verification |
---|---|---|---|---|
MS36 | Pixel optimisation | 40 - UNIMAN | 23 | Report (Task 9.2) |
MS37 | Status report on chimneys | 8 - CNRS | 22 | Report (Task 9.3) |
MS38 | Status report on CRPs | 8 - CNRS | 23 | Report (Task 9.3) |
MS39 | Status report on digitisation | 8 - CNRS | 33 | Report (Task 9.3) |
MS40 |
Large-scale WLS surfaces and SiPMs Tested |
21 - INFN | 22 | Report (Task 9.4) |
Deliverables
D # | Deliverable Name | Lead beneficiary | Type | Due Date (in months) |
---|---|---|---|---|
D9.1 | Large-scale Pixel Anode | 40 - UNIMAN | Report | 44 |
D9.2 |
Vertical Drift chimneys, digitisation, CRPs |
8 - CNRS | Report | 46 |
D9.3 |
R&D in LAr optical readout |
29 - CIEMAT | Report | 45 |