Milestones

Year 1

MS no.

Milestone name

WP

Task

Planned delivery date

Actual delivery date

Status

Comments

MS1 Consortium Agreement signed WP1 1.1 M1   Achieved  
MS4 Launching of project website WP2 2.2 M1 30/04/2021 Achieved Report
MS3 Open RI Innovation Coordination Group WP1 1.3 M6 30/09/2021 Achieved  Report
MS51 Generic R&D projects selected WP13 13.1 M8 01/02/2022 Achieved Confidential
MS41 Combined work plan with objectives and test definition for all technologies WP10 10.2 M11 07/03/2022 Achieved Report
MS7 Analysis of innovations needed in markets and technologies WP2 2.4 M12 17/05/2022 Achieved Report
MS18 High granularity prototype fabrication 1 WP5 5.2 M12 31/03/2022 Achieved Report
MS32 Test benches for testing detecting materials in picosecond and sub-picosecond domains WP8 8.3 M12 31/03/2022 Achieved Report
MS42 Work plan taking also into account the detailed programme announced in MS10.1 WP10 10.3 M12 31/05/2022 Achieved Report

Year 2

MS no.

Milestone name

WP

Task

Planned delivery date

Actual delivery date

Status

Comments

MS6 Young Scientist Publication Committee established WP2 2.3 M15 30/06/2022 Achieved Report
MS30 Conceptual design and technical specifications of DAQ interfaces for highly granular electromagnetic and hadronic calorimeters WP8 8.2 M15 30/09/2022 Achieved Report
MS33 Design and test of scintillating tiles or strips with large active area suitable for large area detectors WP8 8.3 M15   Achieved Report
MS44 Plan of investigation and prototyping for development of mirrorless FSI WP10 10.5 M15 30/10/2022 Achieved Report
MS13 Define requirements, global architecture and design the extended data management system for ENEA-FNG and CERN-GIF++ WP4 4.3 M18 30/10/2022 Achieved Report
MS22 Wafer layout WP6 6.2 M18 09/01/2023 Achieved Report
MS24 Completion of planar sensor production for ACF WP6 6.4 M18 30/10/2022 Achieved Report
MS25 Availability of parts and definition of the technologies for wafer to wafer hybridization WP6 6.4 M18 09/01/2023 Achieved Report
MS34 Definition of SiPM requirements and performance studies with simulations of different use cases WP8 8.4 M18 31/01/2023 Achieved Report
MS45 Design review of 28 nm MPW WP11 11.2 M18   Delayed  
MS46 Design review of 65/130 nm run WP11 11.3 M19 20/12/2022 Achieved Report
MS47 LC reconstruction prototype in Key4hep WP12 12.2 M21 19/01/2023 Achieved Report
MS52 Mid-term review of selected projects WP13 13.2 M21 20/02/2023 Achieved Report
MS37 Status report on chimneys WP9 9.3 M22 25/05/2023 Achieved Report
MS40 Large-scale WLS surfaces and SiPMs Tested WP9 9.4 M22 25/05/2023 Achieved Report
MS43 Mid-time report detailing the new experimental facility and results from the theoretical studies WP10 10.4 M22 31/01/2023 Achieved Report
MS48 Prototype of ML based shower simulation WP12 12.3 M22 24/01/2023 Achieved Report
MS11 Common read-out boards designed WP3 3.5 M23 28/02/2023 Achieved Report
MS12 Upgrade the RBI-AF infrastructure for detector characterisation, SEE, micro hardness testing WP4 4.2 M23 28/02/2023 Achieved Report
MS16 Commission a complete TPA-TCT system WP4 4.4 M23 15/04/2023 Achieved Report
MS17 Apply TF test bench to FEE prototypes WP4 4.5 M23 28/02/2023 Achieved Report
MS20 Radiation hard prototype fabrication WP5 5.3 M23 28/04/2023 Achieved Report
MS23 Preliminary characterisation of 3D and LGAD prototypes. Test set-up ready in the laboratories WP6 6.3 M23 01/05/2023 Achieved Report
MS26 Production of DLC with ion beam deposition and pulsed laser deposition WP7 7.3 M23 28/02/2023 Achieved Report
MS31 Design and simulation of LAr read-out electrode WP8 8.2 M23 30/03/2023 Achieved Report
MS35 Definition of the assembly method and of the ASIC specifications for a dual read-out calorimeter WP8 8.4 M23 28/02/2023 Achieved Report
MS36 Pixel optimisation  WP9 9.2 M23 28/06/2023 Achieved Report
MS38 Status report on CRPs WP9 9.3 M23 30/06/2023 Achieved Report
MS49 Acts tracking algorithm prototypes WP12 12.4 M23 28/02/2023 Achieved Report
MS50 New PFA prototypes WP12 12.5 M23 28/02/2023 Achieved Report
MS5 Academia Meets Industry Symposium WP2 2.2 M24 30/06/2023 Achieved Report

Year 3

MS no.

Milestone name

WP

Task

Planned delivery date

Actual delivery date

Status

Comments

MS8 Telescopes upgraded with ALPIDE sensor WP3 3.2 M27   Delayed Justification for delay
MS10 Monitoring software developed WP3 3.4 M30 30/09/2023 Achieved Report
MS39 Status report on digitisation WP9 9.3 M33   Delayed  
MS9 Timepix4 timing layer in telescopes WP3 3.3 M36      
MS14 Extend IDM for ENEA-FNG, CERN-GIF++ and data communication with CAEN DigiWaste and CANBERRA Apex-Gamma Lab Platforms WP4 4.3 M36 06/02/2024 Achieved Report
MS19 High granularity prototype fabrication 2 WP5 5.2 M36      
MS27 Build a 0.3x0.3 m2 prototype and the read-out plane with the new structure WP7 7.3 M36      
MS28 Identification of a gas mixture for neutrino physics in an optical TPC WP7 7.4 M36 09/04/2024 Achieved Report

Year 4

MS no.

Milestone name

WP

Task

Planned delivery date

Actual delivery date

Status

Comments

MS15 Test RFID tagging for irradiation facilities WP4 4.3 M42    
MS21 Test beam of the radiation hard monolithic pixel 1 WP5 5.3 M42      
MS29 Design electronics for cluster counting and production of a 4-channel prototype  WP7 7.4 M46