WP3: Test beam and DAQ infrastructure

Objectives

Task 3.1 Coordination and Communication
• Management and coordination of the Work Package, including monitoring of work progress, budget spending and
reporting to the project management.
• Organisation of WP meetings as well as meetings with other WPs and coordinating presentation of results within
AIDAinnova and to the detector community.


Task 3.2 Upgrading the EUDET-style beam telescope infrastructure
• Upgrade of the EUDET-style beam reference telescopes with the more recent ALPIDE sensor
• Integration of new AIDAinnova next generation sensors into current telescopes
• Development of a common cold-box for test-beam facilities


Task 3.3 Sub-ns timing capabilities for the EUDET-style telescopes
• Integration of a TimePix4 plane into EUDAQ2
• Picosecond timing support in the AIDA trigger logic unit (TLU)
• Include a plane based on low gain avalanche detectors (LGAD) in the EUDET-style telescopes


Task 3.4 Development of DAQ software for next generation beam tests
• Development of EUDAQ2 software to support picosecond timing of next generation sensors
• Development of versatile online monitoring for EUDAQ2


Task 3.5 Development of common DAQ hardware
• Development of a Caribou-based common readout board to support sensor R&D
• Development of the VMM3 common readout board to support gas detector R&D

Tasks

Task #Task nameTask Leader
3.1Coordination and CommunicationMarcel Stanitzki (DESY), Matthew Wing (UCL)
3.2Upgrading the EUDET-style telescopesAdrian Herkert (DESY)
3.3Sub-ns timing capabilities for the EUDET-style telescopesMartin van Beuzekom (Nikhef), David Cussans (Bristol)
3.4Development of DAQ software for next generation beam testsLennart Huth (DESY)
3.5Development of common DAQ hardwareDominik Dannheim (CERN)

Milestones

MS #Milestone nameLead beneficiaryDue Date (in months)Means of verification
MS8Telescopes upgraded with ALPIDE sensor12 – DESY27New telescope in test-beam facilities (Task 3.2)
MS9Timepix4 timing layer in telescopes23 – NWO-I/Nikhef36Upgraded telescope in all beamlines (Task 3.3)
MS10Monitoring software developed39 – UCL30Use in beam tests (Task 3.4)
MS11Common readout boards designed1 – CERN23Prototype developed (Task 3.5)

Deliverables

D #Deliverable nameLead beneficiaryTypeDue Date (in months)
D3.1Common cold box delivered1 – CERNReport30
D3.2New TLU produced38 – UNIVBRISDemonstrator39
D3.3Telescopes upgraded with new layers12 – DESYDemonstrator46
D3.4New software developments available for use39 – UCLReport39
D3.5Common readout boards delivered1 – CERNReport42