Year 1
MS no. |
Milestone name |
WP |
Task |
Planned delivery date |
Actual delivery date |
Status |
Comments |
---|---|---|---|---|---|---|---|
MS1 | Consortium Agreement signed | WP1 | 1.1 | M1 | Achieved | ||
MS4 | Launching of project website | WP2 | 2.2 | M1 | 30/04/2021 | Achieved | Report |
MS3 | Open RI Innovation Coordination Group | WP1 | 1.3 | M6 | 30/09/2021 | Achieved | Report |
MS51 | Generic R&D projects selected | WP13 | 13.1 | M8 | 01/02/2022 | Achieved | Confidential |
MS41 | Combined work plan with objectives and test definition for all technologies | WP10 | 10.2 | M11 | 07/03/2022 | Achieved | Report |
MS7 | Analysis of innovations needed in markets and technologies | WP2 | 2.4 | M12 | 17/05/2022 | Achieved | Report |
MS18 | High granularity prototype fabrication 1 | WP5 | 5.2 | M12 | 31/03/2022 | Achieved | Report |
MS32 | Test benches for testing detecting materials in picosecond and sub-picosecond domains | WP8 | 8.3 | M12 | 31/03/2022 | Achieved | Report |
MS42 | Work plan taking also into account the detailed programme announced in MS10.1 | WP10 | 10.3 | M12 | 31/05/2022 | Achieved | Report |
Year 2
MS no. |
Milestone name |
WP |
Task |
Planned delivery date |
Actual delivery date |
Status |
Comments |
---|---|---|---|---|---|---|---|
MS6 | Young Scientist Publication Committee established | WP2 | 2.3 | M15 | 30/06/2022 | Achieved | Report |
MS30 | Conceptual design and technical specifications of DAQ interfaces for highly granular electromagnetic and hadronic calorimeters | WP8 | 8.2 | M15 | 30/09/2022 | Achieved | Report |
MS33 | Design and test of scintillating tiles or strips with large active area suitable for large area detectors | WP8 | 8.3 | M15 | Achieved | Report | |
MS44 | Plan of investigation and prototyping for development of mirrorless FSI | WP10 | 10.5 | M15 | 30/10/2022 | Achieved | Report |
MS13 | Define requirements, global architecture and design the extended data management system for ENEA-FNG and CERN-GIF++ | WP4 | 4.3 | M18 | 30/10/2022 | Achieved | Report |
MS22 | Wafer layout | WP6 | 6.2 | M18 | 09/01/2023 | Achieved | Report |
MS24 | Completion of planar sensor production for ACF | WP6 | 6.4 | M18 | 30/10/2022 | Achieved | Report |
MS25 | Availability of parts and definition of the technologies for wafer to wafer hybridization | WP6 | 6.4 | M18 | 09/01/2023 | Achieved | Report |
MS34 | Definition of SiPM requirements and performance studies with simulations of different use cases | WP8 | 8.4 | M18 | 31/01/2023 | Achieved | Report |
MS45 | Design review of 28 nm MPW | WP11 | 11.2 | M18 | 07/02/2023 | Achieved | Report |
MS46 | Design review of 65/130 nm run | WP11 | 11.3 | M19 | 20/12/2022 | Achieved | Report |
MS47 | LC reconstruction prototype in Key4hep | WP12 | 12.2 | M21 | 19/01/2023 | Achieved | Report |
MS52 | Mid-term review of selected projects | WP13 | 13.2 | M21 | 20/02/2023 | Achieved | Report |
MS37 | Status report on chimneys | WP9 | 9.3 | M22 | 25/05/2023 | Achieved | Report |
MS40 | Large-scale WLS surfaces and SiPMs Tested | WP9 | 9.4 | M22 | 25/05/2023 | Achieved | Report |
MS43 | Mid-time report detailing the new experimental facility and results from the theoretical studies | WP10 | 10.4 | M22 | 31/01/2023 | Achieved | Report |
MS48 | Prototype of ML based shower simulation | WP12 | 12.3 | M22 | 24/01/2023 | Achieved | Report |
MS11 | Common read-out boards designed | WP3 | 3.5 | M23 | 28/02/2023 | Achieved | Report |
MS12 | Upgrade the RBI-AF infrastructure for detector characterisation, SEE, micro hardness testing | WP4 | 4.2 | M23 | 28/02/2023 | Achieved | Report |
MS16 | Commission a complete TPA-TCT system | WP4 | 4.4 | M23 | 15/04/2023 | Achieved | Report |
MS17 | Apply TF test bench to FEE prototypes | WP4 | 4.5 | M23 | 28/02/2023 | Achieved | Report |
MS20 | Radiation hard prototype fabrication | WP5 | 5.3 | M23 | 28/04/2023 | Achieved | Report |
MS23 | Preliminary characterisation of 3D and LGAD prototypes. Test set-up ready in the laboratories | WP6 | 6.3 | M23 | 01/05/2023 | Achieved | Report |
MS26 | Production of DLC with ion beam deposition and pulsed laser deposition | WP7 | 7.3 | M23 | 28/02/2023 | Achieved | Report |
MS31 | Design and simulation of LAr read-out electrode | WP8 | 8.2 | M23 | 30/03/2023 | Achieved | Report |
MS35 | Definition of the assembly method and of the ASIC specifications for a dual read-out calorimeter | WP8 | 8.4 | M23 | 28/02/2023 | Achieved | Report |
MS36 | Pixel optimisation | WP9 | 9.2 | M23 | 28/06/2023 | Achieved | Report |
MS38 | Status report on CRPs | WP9 | 9.3 | M23 | 30/06/2023 | Achieved | Report |
MS49 | Acts tracking algorithm prototypes | WP12 | 12.4 | M23 | 28/02/2023 | Achieved | Report |
MS50 | New PFA prototypes | WP12 | 12.5 | M23 | 28/02/2023 | Achieved | Report |
MS5 | Academia Meets Industry Symposium | WP2 | 2.2 | M24 | 30/06/2023 | Achieved | Report |
Year 3
MS no. |
Milestone name |
WP |
Task |
Planned delivery date |
Actual delivery date |
Status |
Comments |
---|---|---|---|---|---|---|---|
MS8 | Telescopes upgraded with ALPIDE sensor | WP3 | 3.2 | M27 | Delayed | Justification for delay | |
MS10 | Monitoring software developed | WP3 | 3.4 | M30 | 30/09/2023 | Achieved | Report |
MS39 | Status report on digitisation | WP9 | 9.3 | M33 | 01/03/2024 | Achieved | Report |
MS9 | Timepix4 timing layer in telescopes | WP3 | 3.3 | M36 | 30/09/2024 | Delayed | Justification for delay |
MS14 | Extend IDM for ENEA-FNG, CERN-GIF++ and data communication with CAEN DigiWaste and CANBERRA Apex-Gamma Lab Platforms | WP4 | 4.3 | M36 | 06/02/2024 | Achieved | Report |
MS19 | High granularity prototype fabrication 2 | WP5 | 5.2 | M36 | 06/05/2024 | Achieved | Report |
MS27 | Build a 0.3x0.3 m2 prototype and the read-out plane with the new structure | WP7 | 7.3 | M36 | 25/09/2024 | Achieved | Report |
MS28 | Identification of a gas mixture for neutrino physics in an optical TPC | WP7 | 7.4 | M36 | 09/04/2024 | Achieved | Report |
Year 4
MS no. |
Milestone name |
WP |
Task |
Planned delivery date |
Actual delivery date |
Status |
Comments |
---|---|---|---|---|---|---|---|
MS15 | Test RFID tagging for irradiation facilities | WP4 | 4.3 | M42 | |||
MS21 | Test beam of the radiation hard monolithic pixel 1 | WP5 | 5.3 | M42 | |||
MS29 | Design electronics for cluster counting and production of a 4-channel prototype | WP7 | 7.4 | M46 |